Real Life Accident: Rescue Boat Falls In Water During Drill With Crew Members Inside, One Dies

The crew of a large vessel was conducting a routine launching drill of a rescue boat in port. As the craft was coming up to its normal stowage position, a proximity sensor/limit or cut-off switch arrangement (Figure 1) that was designed to cut electrical power to the winch motor failed to operate correctly. With the davit having come up hard against its stops, the hoisting motor continued to wind in the fall wire, causing it to part. The rescue boat and its four crew fell 29 meters into the water. One of the boat’s crew died and two were hospitalised.

The parted fall wire was observed to be in good condition and when tested after the accident, it achieved a breaking load of 137kN.

Although the winch motor was rated with a nominal pull of 50kN, the maximum pull that it was capable of exerting when trying to overcome the increased resistance in the system during the final stages of hoisting would have rapidly exceeded the breaking load of the wire.

Image for representation purpose only.
Image for representation purpose only.

The proximity sensor/limit switch was tested in situ and was found to be defective. It had been installed in 2006, and during the ill-fated drill, was not tested before hoisting was commenced. Inspection revealed evidence of water ingress (Figure 2), although subsequent tests showed that the switch malfunctioned due to an unrelated electronic fault.

proximity sensor switch

During the investigations, it was also unexpectedly discovered that water had entered the foam-filled buoyancy spaces between the inner and outer fibreglass skins of the rescue boat’s hull (Figures 3 & 4). The craft was found to be approximately 450 kg overweight. Although the additional weight of water caused the davit’s SWL to be exceeded, it was established that this would not have caused the wire to fail.

Lessons learnt

  • The maximum pull of a hoist winch can exceed its nominal pull several-fold, and therefore is likely to exceed the breaking loads of other system components unless this is prevented by a properly functioning ‘final stop’ or safety device;
  • The proximity sensor/limit switch fitted to the davit was considered by its manufacturer to be inappropriate for use as a ‘final stop’ or safety device. Operators of all vessels fitted with similar davits and safety devices must understand the potential limitations of the switches and take immediate and appropriate corrective actions;

water ingress within proximity sensor

  • The proximity switch was incorrectly fitted with its cable entry gland higher than the switch body thereby increasing the possibility of water ingress.

Corrective/preventative actions by davit makers

A notification was issued to customers advising them to:

  • Test all proximity switches on each occasion before hoisting operations commence;

water in bouyancy space

  • Replace all proximity switches every two years;
  • Exercise caution when using pressure washers in the vicinity of these sensors/switches.

Main recommendations for ship operators

  • Ensure that all devices (inductive or mechanical) fitted to boat davit systems to prevent overload are tested on each occasion before a boat is hoisted and that sole reliance is not placed on such devices;

draining of accumuated water

  • Follow manufacturers’ recommendations regarding the maintenance and periodic testing, examination and replacement of safety devices, seeking clarification from manufacturers where ambiguity exists;
  • Verify the effectiveness of watertight seals on electrical equipment fitted to boat davit systems on weather decks.

Reference & Image Credits: nautinst

Do you have info to share with us ? Suggest a correction

Article Footer Banner
Article Footer Banner

Subscribe To Our Newsletters

By subscribing, you agree to our Privacy Policy and may receive occasional deal communications; you can unsubscribe anytime.

Web Stories

7 Comments

  1. Fisrt, there was no reason to keep the 4 crew members on board during the last stage to bring home the rescue boad!!!!!

  2. when retrieving the rescue boat and upon reaching the “disembarkation level” on board crew (usually 4) must disembark here before placing the rescue boat back to its original stowage position. Highest tension for both boat falls and boat winch are experienced at this point. Lowering and retrieving exercise without the 4 crew compliments first is best to test for any abnormalities. But with boarding crew is MUST,

  3. For such a detailed article with conclusions based on technical analysis facts it is really impressive that nobody noticed the fall wire was not actually torn/parted… none of the two.

  4. 1) Preventer wire should be fitted when the boat was just above the water level, only after this fitting the boat should be hoisted up
    2) All boat crews should disembark when the boat reached embarkation

  5. Nowadays common practice to many is not to have personnel inside during lowering and hoisting of lifeboats. They have to board and leave the lifeboats , while in the water , by other means .

Leave a Reply

Your email address will not be published. Required fields are marked *