US Navy Plans 600-Ton Hypersonic Launcher For 12 Missiles On Destroyer USS Michael Monsoor
USS Michael Monsoor would receive a 600-ton launch module for hypersonic missiles under a US Navy plan to turn the Zumwalt-class destroyer into a long-range strike ship.
Naval Sea Systems Command (NAVSEA) published two notices on November 17, 2026, which set out the industrial requirements for the work. One notice covers the installation of the Large Missile Vertical Launch System (LMVLS), while the other announces an industry meeting in Washington on December 9.
The modernization period for the second ship of the Zumwalt class is planned from May 2028 till August 2030. The notices are only part of industrial preparations and do not amount to a contract award for the installation, according to reports.
The prefabricated module for USS Michael Monsoor would measure around 13.6 metres long, 6.3 metres wide and 12.5 metres high. Its four large launch tubes would hold up to 12 Conventional Prompt Strike (CPS) hypersonic missiles, with three missiles carried in each tube. The module would take the place of the 155mm Advanced Gun System (AGS) in the forward section of the destroyer.
The destroyer has a tumblehome hull with inward-sloping sides, which complicates stability, weight distribution and access during the installation. The US Navy is studying the heavy-lift cranes and handling equipment that shipyards would need to fit the module without distorting the hull.
The CPS missile uses a two-stage rocket booster which accelerates a glide body that then separates and maneuvers towards its target at over five times the speed of sound. On warships, the missile relies on a cold-gas system which ejects it from the tube before the booster ignites, thereby reducing stress on the vessel.
The US Navy and the US Army are jointly developing the missile, which the Army calls the Long-Range Hypersonic Weapon.
A Government Accountability Office report from July 2026 found that the effort to modernize all three Zumwalt-class destroyers for the missile was running 24 months behind schedule. The report also said the production facility for the missile can build only six to seven rounds a year, against the 12 rounds needed to stabilize production.
The first CPS flight test from a Zumwalt-class ship has now moved to 2027 after it was originally planned for 2025.
The lead ship USS Zumwalt was 94% through its own modernization as of January 2026, while the third ship USS Lyndon B. Johnson would also get the hypersonic upgrade.
References: Army Recognition, Interesting Engineering, US Government Accountability Office
RELATED POSTS
Disclaimer :
The information on this website is for general purposes only. While efforts are made to ensure accuracy, we make no warranties of any kind regarding completeness, reliability, or suitability. Any reliance you place on such information is at your own risk. We are not liable for any loss or damage arising from the use of this website.
About Author
Zahra is a maritime writer with 6 years of technical writing experience spanning port operations, offshore wind, oil and gas, and maritime policy. Her analytical edge...Read More ->
Disclaimer :
The information on this website is for general purposes only. While efforts are made to ensure accuracy, we make no warranties of any kind regarding completeness, reliability, or suitability. Any reliance you place on such information is at your own risk. We are not liable for any loss or damage arising from the use of this website.
Subscribe To Our Daily Newsletter
By subscribing, you agree to our Privacy Policy you can unsubscribe anytime.