Photos: World’s Largest Vessel ‘Pioneering Spirit’ Removes Third Platform From Brent Field

Allseas’ heavy lift vessel Pioneering Spirit has completed its first decommissioning job of this summer, the single-lift removal of Shell U.K. Limited’s Brent Alpha platform from the North Sea.

Pioneering Spirit in the Brent field
Image Credits: allseas.com

Several years of planning and 15 months of offshore preparation, including strengthening and cutting the steel jacket’s six legs, culminated in the 9-second “fast lift” of the 17,000-t topsides in the evening of 21 June 2020.

Pioneering Spirit will now deliver the 44-year old structure to Able UK Limited’s Teesside decommissioning yard in North East England for dismantling and recycling.

Pioneering Spirit moving-in-around-the-Alpha-platform
Image Credits: allseas.com

Brent Alpha is the third of four platforms, after Delta (2017) and Bravo (2019), to be decommissioned and removed from the Brent oil and gas field. For all four jobs, Shell UK Limited selected Pioneering Spirit. Production from the field continues through Brent Charlie, with Pioneering Spirit booked to remove the 34,000-t topsides when the platform finally ceases production.

Pioneering Spirit Connecting the horseshoes
Image Credits: allseas.com

Located 186 km off the northeast coast of the Shetland Islands, Brent Alpha comprised a topsides structure supported by a steel six-legged jacket standing in 140 m of water. Like Delta and Bravo, the Alpha topsides features multiple decks with living quarters, power generation, process systems, drilling derrick, flare stack and other platform facilities.

Pioneering Spirit Moving away from the jacket
Image Credits: allseas.com

The removal of Brent Alpha is the first offshore lift to utilize specially developed “horseshoes”: connection tools that clamp around pre-installed lift points called bearing brackets mounted on the upper sections of the steel jacket’s legs.

Fast lift of the Alpha topsides
Image Credits: allseas.com

The Brent Alpha topsides removal project involves engineering, preparation, removal, and disposal of the 94 m tall, 52 m wide structure. As with the two previous Brent jobs, Pioneering Spirit will transport the Alpha topsides to a nearshore location off the Hartlepool coastline, where it will be transferred to Allseas’ cargo barge Iron Lady for the final leg of its journey by towage up the Seaton Channel and load-in to the quay at Able UK.

Moving-away-from-the-jacket
Image Credits: allseas.com

This summer, Pioneering Spirit will remove and transport more than 55,000 t of decommissioned platform infrastructure from UK and Danish fields to disposal/recycling yards around the North Sea.

Reference: allseas.com

Disclaimer :
The information contained in this website is for general information purposes only. While we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.

In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.

Do you have info to share with us ? Suggest a correction

Latest Shipping News You Would Like:

Get the Latest Maritime News Delivered to Your Inbox!

Our free, fast, and fun newsletter on the global maritime industry, delivered everyday.

Leave a Reply

Your email address will not be published. Required fields are marked *