Jan De Nul Completes Foundation And Cable Installation On The Formosa 2 Offshore Wind Farm
Jan De Nul Group finalised the installation of 47 jacket foundations and 188 pin piles, 4 export and 47 inter array cables for the construction of Formosa 2 Offshore Wind Farm in Taiwan.
The achievement of this momentous milestone places Jan De Nul Group firmly on the final straight towards delivering the EPCI Formosa 2 Offshore Wind Farm contract in the coming weeks.
Thanks to a multidisciplinary approach and early involvement of local suppliers, Jan De Nul Group remains an excellent partner to assist its Clients in realising their ambitions to execute larger and more complex projects.
Jan De Nul Group successfully completed the installation of the 47 jacket foundations and 188 pin piles, the 4 export and 47 inter array cables on the Formosa 2 Offshore Wind Farm in Taiwan. With the achievement of these major milestones, Jan De Nul brings its EPCI scope onto the final straight towards completion in the coming weeks.
188 pin piles
Jan De Nul subcontracted EEW KHPC for the fabrication of 188 pin piles, some with a weight of over 270 tonnes and a length up to 79 metres.
In 2020, the piles were transported from the fabrication yards in South-Korea and Malaysia to the marshalling harbour in Taichung, Taiwan. Heavy Lift Vessel Seaway Yudin commenced installing the piles in water depths up to 55 metres, with the final pile installed on 22 August 2022.
During the installation activities, Jan De Nul also managed the underwater noise monitoring and marine mammal observation in compliance with the environmental restrictions and permits.
47 jacket foundations
Jan De Nul ordered the jacket foundations from Sembcorp Marine Ltd. and Saipem S.A. Fabrication at the yards in Indonesia commenced in 2020. With a height of up to 91 metres and a weight of over 1,600 tonnes, they are amongst the largest and heaviest jackets in the offshore wind industry, equalling the height of a typical 30-floor building.
From October 2021 to July 2022, three heavy transport vessels delivered all jackets to the marshalling harbour for intermediate storage and final preparation before installation, which commenced in April 2022 with Heavy Lift Vessel Bokalift 1.
The final jacket was installed on 26 August 2022, thereby completing the foundation fabrication and installation scope.
4 export and 47 inter-array cables
In 2020, Jan De Nul subcontracted the manufacturing of 34.5 km of export cables and 87 km of inter-array cables to LS Cable. Jan De Nul’s shallow water Cable-Laying Vessel Willem de Vlamingh and Multipurpose Vessel Connector picked up, transported and installed the cables in 2021 and 2022 respectively. Both vessels also acted as trenching support vessel to bury the cables with a jet trencher in certain sections of the cable routes. Jan De Nul’s Trailing Suction Hopper Dredger Niña and Francis Beaufort performed pre-trenching in the harder sections.
The four export cables were pulled through the drilled HDD pipes nearshore in 2021, and were finally joined onshore with the land cables at the transition joint bays. Installation of the 47 inter-array cables commenced in May 2022 and was completed on 1 September.
In the coming weeks, Offshore Support Vessel Orient Constructor of local partner DFO will continue facilitating walk-to-work access for the teams finalising the terminations of the cables, allowing the energization of the entire wind farm.
Offshore Support Vessel Grand Canyon 2 and Jan De Nul’s Connector will complete the remaining cable burials and stabilizations in the course of September.
Press Release
Shipping News You Would Like:
Disclaimer :
The information contained in this website is for general information purposes only. While we endeavour to keep the information up to date and correct, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information, products, services, or related graphics contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.
In no event will we be liable for any loss or damage including without limitation, indirect or consequential loss or damage, or any loss or damage whatsoever arising from loss of data or profits arising out of, or in connection with, the use of this website.
Do you have info to share with us ? Suggest a correction
Latest Shipping News You Would Like:
Ukraine Claims Killing Russia’s Black Sea Fleet Commander And 33 Officers In Crimean Attack
New Port Welcomes The Biggest Cruise Ship Of the Season MSC Meravigilia
US Navy Announces Firing Captain Of Missile Submarine USS Alabama For Loss Of Confidence
China Building A StarWars Style SuperShip To Strengthen Its Naval Fleet For Countering U.S
Sri Lanka Denies Permission To Chinese Ship To Dock, Says Indian Security Concerns Important For Colombo
Get the Latest Maritime News Delivered to Your Inbox!
Our free, fast, and fun newsletter on the global maritime industry, delivered everyday.